Light Rail Stage 2A

Feb 20, 2025

King Edward Terrace & surrounding area.

Location: King Edward Terrace between Flynn Drive, Newlands Street and Mall Road West. 

Work description: Temporary work areas will be set up in the construction zone. Utilities in the ground will continue to be relocated. 

Impacts: To minimise disruption to vehicle traffic, cyclists and pedestrians during the day, some activities will be undertaken outside of standard construction hours between 8pm and 5am. Temporary lane closures will occur to support out of hours activities.

Works to relocate utilities through the intersection of King Edward Terrace and Flynn Drive/Langton Crescent will be undertaken in March. To enable these works there will be a temporary intersection closure between the hours of 8pm and 4am on weeknights for up to 1 week during construction. 

A detour around the intersection will be in place for vehicles during these works. Pedestrian access and thoroughfares will not change.

Some carparks in Langton car park will be reduced for up to 1 week during construction.